PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE:

After the above mentioned conditions are fulfilled, the following steps shall be taken:
Write a letter /email to builder/ promoter requesting him to provide a draft of the SALE DEED/ CONVEYANCE DEED or providing the draft to him and requesting him to sign the same.
• If the Builder rejects or postpones the same, send him a legal notice through an advocate requesting for the same.
• Even then if the builder refuses, File an application with the Registrar of Co-operative Societies together with all the relevant documents and 2000 Rs. Court stamp fees.
• Self-attestation all the copies enclosed (by the society)
• The Competent Authority will assess the application and if any documents are missing he will ask the applicant to correct the mistake within fifteen days.
• Thereafter, notice would be sent to the promoter and the land owners.
• After receipt of the notice by the land owners and the promoters, the authority will hear both parties in the first hearing and ask both parties to produce further evidences in next hearing.
• Thereafter, second hearing would be held and if the builder or landowners do not attend both first and second hearing then the authority will pass an exparte order.
• Thereafter, the third and final hearing would be held and the authority would be held and order would be passed unless a legal question is raised.
• Normally the whole process is completed within a period of 6 months.

By |October 4th, 2019|PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE|Comments Off on PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

After the above mentioned conditions are fulfilled, the following steps shall be taken:
Write a letter /email to builder/ promoter requesting him to provide a draft of the SALE DEED/ CONVEYANCE DEED or providing the draft to him and requesting him to sign the same.
• If the Builder rejects or postpones the same, send him a legal notice through an advocate requesting for the same.
• Even then if the builder refuses, File an application with the Registrar of Co-operative Societies together with all the relevant documents and 2000 Rs. Court stamp fees.
• Self-attestation all the copies enclosed (by the society)
• The Competent Authority will assess the application and if any documents are missing he will ask the applicant to correct the mistake within fifteen days.
• Thereafter, notice would be sent to the promoter and the land owners.
• After receipt of the notice by the land owners and the promoters, the authority will hear both parties in the first hearing and ask both parties to produce further evidences in next hearing.
• Thereafter, second hearing would be held and if the builder or landowners do not attend both first and second hearing then the authority will pass an exparte order.
• Thereafter, the third and final hearing would be held and the authority would be held and order would be passed unless a legal question is raised.
• Normally the whole process is completed within a period of 6 months.

By |September 5th, 2019|PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE|Comments Off on PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE:

After the above mentioned conditions are fulfilled, the following steps shall be taken:
Write a letter /email to builder/ promoter requesting him to provide a draft of the SALE DEED/ CONVEYANCE DEED or providing the draft to him and requesting him to sign the same.
• If the Builder rejects or postpones the same, send him a legal notice through an advocate requesting for the same.
• Even then if the builder refuses, File an application with the Registrar of Co-operative Societies together with all the relevant documents and 2000 Rs. Court stamp fees.
• Self-attestation all the copies enclosed (by the society)
• The Competent Authority will assess the application and if any documents are missing he will ask the applicant to correct the mistake within fifteen days.
• Thereafter, notice would be sent to the promoter and the land owners.
• After receipt of the notice by the land owners and the promoters, the authority will hear both parties in the first hearing and ask both parties to produce further evidences in next hearing.
• Thereafter, second hearing would be held and if the builder or landowners do not attend both first and second hearing then the authority will pass an exparte order.
• Thereafter, the third and final hearing would be held and the authority would be held and order would be passed unless a legal question is raised.
• Normally the whole process is completed within a period of 6 months.

By |August 30th, 2019|PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE|Comments Off on PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE:

After the above mentioned conditions are fulfilled, the following steps shall be taken:
Write a letter /email to builder/ promoter requesting him to provide a draft of the SALE DEED/ CONVEYANCE DEED or providing the draft to him and requesting him to sign the same.
• If the Builder rejects or postpones the same, send him a legal notice through an advocate requesting for the same.
• Even then if the builder refuses, File an application with the Registrar of Co-operative Societies together with all the relevant documents and 2000 Rs. Court stamp fees.
• Self-attestation all the copies enclosed (by the society)
• The Competent Authority will assess the application and if any documents are missing he will ask the applicant to correct the mistake within fifteen days.
• Thereafter, notice would be sent to the promoter and the land owners.
• After receipt of the notice by the land owners and the promoters, the authority will hear both parties in the first hearing and ask both parties to produce further evidences in next hearing.
• Thereafter, second hearing would be held and if the builder or landowners do not attend both first and second hearing then the authority will pass an exparte order.
• Thereafter, the third and final hearing would be held and the authority would be held and order would be passed unless a legal question is raised.
• Normally the whole process is completed within a period of 6 months.

By |August 14th, 2019|PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE|Comments Off on PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE:

PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE:

There are certain important conditions which need to be fulfilled to go ahead for deemed conveyance, some of them are:

1. At least 60% of the flats in that scheme should be sold.
2. A Co-operative Society or Association of Persons should have been formed of the flat-owners and at least 3-4 months should have been passed since then.
3. There should be communication between the builder and the society or AOP regarding Deemed Conveyance wherein the builder should have made a promise of completion of conveyance or refused to do the same.

After the above mentioned conditions are fulfilled, the following steps shall be taken:
Write a letter /email to builder/ promoter requesting him to provide a draft of the SALE DEED/ CONVEYANCE DEED or providing the draft to him and requesting him to sign the same.
• If the Builder rejects or postpones the same, send him a legal notice through an advocate requesting for the same.
• Even then if the builder refuses, File an application with the Registrar of Co-operative Societies together with all the relevant documents and 2000 Rs. Court stamp fees.
• Self-attestation all the copies enclosed (by the society)
• The Competent Authority will assess the application and if any documents are missing he will ask the applicant to correct the mistake within fifteen days.
• Thereafter, notice would be sent to the promoter and the land owners.
• After receipt of the notice by the land owners and the promoters, the authority will hear both parties in the first hearing and ask both parties to produce further evidences in next hearing.
• Thereafter, second hearing would be held and if the builder or landowners do not attend both first and second hearing then the authority will pass an exparte order.
• Thereafter, the third and final hearing would be held and the authority would be held and order would be passed unless a legal question is raised.
• Normally the whole process is completed within a period of 6 months.

By |November 26th, 2018|PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE|Comments Off on PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE:

PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

After the above mentioned conditions are fulfilled, the following steps shall be taken:
Write a letter /email to builder/ promoter requesting him to provide a draft of the SALE DEED/ CONVEYANCE DEED or providing the draft to him and requesting him to sign the same.
• If the Builder rejects or postpones the same, send him a legal notice through an advocate requesting for the same.
• Even then if the builder refuses, File an application with the Registrar of Co-operative Societies together with all the relevant documents and 2000 Rs. Court stamp fees.
• Self-attestation all the copies enclosed (by the society)
• The Competent Authority will assess the application and if any documents are missing he will ask the applicant to correct the mistake within fifteen days.
• Thereafter, notice would be sent to the promoter and the land owners.
• After receipt of the notice by the land owners and the promoters, the authority will hear both parties in the first hearing and ask both parties to produce further evidences in next hearing.
• Thereafter, second hearing would be held and if the builder or landowners do not attend both first and second hearing then the authority will pass an exparte order.
• Thereafter, the third and final hearing would be held and the authority would be held and order would be passed unless a legal question is raised.
• Normally the whole process is completed within a period of 6 months.

By |October 29th, 2018|PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE|Comments Off on PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

After the above mentioned conditions are fulfilled, the following steps shall be taken:

Write a letter /email to builder/ promoter requesting him to provide a draft of the SALE DEED/ CONVEYANCE DEED or providing the draft to him and requesting him to sign the same.

  • If the Builder rejects or postpones the same, send him a legal notice through an advocate requesting for the same.
  • Even then if the builder refuses, File an application with the Registrar of Co-operative Societies together with all the relevant documents and 2000 Rs. Court stamp fees.
  • Self-attestation all the copies enclosed (by the society)
  • The Competent Authority will assess the application and if any documents are missing he will ask the applicant to correct the mistake within fifteen days.
  • Thereafter, notice would be sent to the promoter and the land owners.
  • After receipt of the notice by the land owners and the promoters, the authority will hear both parties in the first hearing and ask both parties to produce further evidences in next hearing.
  • Thereafter, second hearing would be held and if the builder or landowners do not attend both first and second hearing then the authority will pass an exparte order.
  • Thereafter, the third and final hearing would be held and the authority would be held and order would be passed unless a legal question is raised.
  • Normally the whole process is completed within a period of 6 months.

DOCUMENTS REQUIRED:

Further, the application required to be made with the Registrar shall be accompanied by copies of certain 20 odd documents which the society shall have to prepare or get prepared.

 

The papers required for doing Deemed Conveyance are as follows:

  • Application Form 7 to the District Deputy Registrar, Co-operative Societies, affixing a court fee stamp of Rs 2,000 on the application
  • Affidavit made before the Notary or Executive Magistrate True copy of the Society Registration Certificate
  • Stamp duty paid and registered agreement copy of 1 individual flats/ shops with Builder/Developer
  • List of members in prescribed format
  • Index-II for each member as issued by the Sub-Registrar of Assurance
  • Copy of the Development Agreement between land owner and builder
  • Copy of the Power of Attorney between land owner and builder
  • Copy of the legal notice issued to the original owner or developer for doing conveyance
  • Details of corresponding address telephone number etc. of the original owner or developer
  • Draft conveyance deed/ Declaration proposed to be executed in favour of the applicant

 

Documents to be obtained from City Survey Office, for submission:

  • City (CTS) Survey plan
  • Property Registration Card or
  • 7/12 extract of the land
  • Village form 6 (Mutation entries from Revenue Office)

 

Documents to be obtained from the Collector’s Office, for submission:

  • Copy of the Non-Agricultural Order
  • Certificate of the exclusion from Land Ceiling Act (ULC) Certificate

 

Documents to be obtained from the concerned Municipal Authority Office, for submission:

  • Copy of the approved plan
  • IOD
  • Commencement Certificate
  • Building Completion certificate
  • Occupation Certificate (not compulsory)
  • Property taxes paid
  • Location plan of the building

 

Documents to be obtained from other professionals, for submission:

  • Search Report of the land issued by the Solicitor/Advocate
  • Title Certificate of the Property issued by the Solicitor/Advocate (Search by minimum for last 30 years)
  • Land Measurement Map/ Architect’s Certificate (layout plan of the plot)
  • Certified copy from Panel Architect about the utilization of full FSI or FSI if any left in respect of the said property /Plot.

After, the Application is heard by the Registrar he may grant an order for deemed conveyance which shall then be produced before a court for execution and hence the conveyance may be done by a court order.

PROCEDURE:

Stage 1- Preparation for Deemed Conveyance
During this stage the Managing Committee prepares the Members of the Co- Operative Housing Society for Deemed Conveyance.

Stage 2- Documentation for Deemed Conveyance
During this stage the Documents Required for Deemed Conveyance are collected/ organized & the Case is prepared.

Stage 3- Legal Case for Deemed Conveyance
During this stage the case is filed before the Competent Authority & after contesting the same the Order & Certificate upholding the right of Deemed Conveyance of the Society is obtained.

Stage 4- Registration of Deemed Conveyance
During this stage the Deemed Conveyance Deed is Adjudicated, properly Stamped & Registered.

Stage 5- Transfer of Property after Deemed Conveyance
During this stage the Society Name is incorporated in the Land Revenue Records.

Let’s discuss each step in detail:

 

  1. Preparation for Deemed Conveyance:

In this stage the managing committee needs to pass resolution to undergo deemed conveyance. A Special General Meeting is scheduled with prior notification and consent of all the members is obtained to move ahead.

 

During this SGM the following Resolutions are typically passed.

  1. Resolution for going ahead with Deemed Conveyance
  2. Resolution for Appointment of Authorized Representative
  3. Resolution for Appointment of Legal Consultant for Deemed Conveyance
  4. Resolution for Per Member Contributions
  1. Documentation for Deemed Conveyance:

This is the most crucial step in obtaining deemed conveyance. It is a very meticulous job and make sure all the documents are lined up within the right format. You would require land revenue records, municipal corporation records, society records, property development records and professional certificates.

All these documents can be obtained from various departments such as Land revenue records from City Survey Office, Tahasildar/Talathi Office & District Collector Office, municipal corporation records from Building Proposal Department of the Municipal Corporation. Society records and certificates can be obtained from society offices and professionals.

Once all the documents are lined up, society needs to fill in Deemed Conveyance Application- Form VII and attached all the related documents. In case of deemed conveyance, a legal notice is sent to the developer for their consent. In regular conveyance procedures, since the developers or promoters are willingly providing the rights lot of documents can be easily recovered from them.

Once the form is filled up and all documents are annexed it is submitted to the Competent Authority- the District Deputy Registrar of Co- Operative Societies of the particular District.

  1. Legal Case for deemed conveyance:

Once the application is submitted to the authorities they issue Deemed Conveyance Scrutiny Report- Form VIII within 1 month. Once the compliance is provided the authorities issues Summons & Newspaper Notices to the Land Owners & Property Developers for appearing for the hearing.

During the hearing process authorities take into consideration the arguments of the both parties. The process takes place within 3-4 months. Once all the arguments are documented the office issues a Deemed Conveyance order within 1 month. The whole process is completed within 6 months as this is a time bound activity.

  1. Registration of deemed conveyance:

A deemed conveyance deed is created during this phase and is signed by both societies and developers. If developers do not appear for hearing in the prior stage (Which is the case in deemed conveyance), authorities have the power to sign the deed on behalf of developers.

The society needs to conduct a meeting and appoint 3 members to sign the deed. Post that the deed is submitted to district stamp office for adjudication. If all the members have paid their stamp duty and if there is no balance FSI, the office issues adjudication certificate. (Note – Deed only requires Rs 100 stamp duty). The adjudication certificate needs to be then franked from local bank and resubmitted to registration office.

The registration office then issues notice to land owner/developer to verify if there is any stay order against the deed of conveyance. (Note – The developer can get the stay order only from high court). If there is no stay order the deed of deemed conveyance is registered and then the office issues scanned documents and Index II. This mark end of registration process and the society becomes the owner of the land and structure.

  1. Transfer of property:

In this phase a new application is submitted to various departments to make mutation entries in their records. This would make the process complete.

FOR MORE DETAILS CALL:

VED LEGAL,

Adv. Gajanan Rahate

Mob: 9763040088

E_mail: [email protected]

By |July 5th, 2018|PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE|Comments Off on PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

After the above mentioned conditions are fulfilled, the following steps shall be taken:

Write a letter /email to builder/ promoter requesting him to provide a draft of the SALE DEED/ CONVEYANCE DEED or providing the draft to him and requesting him to sign the same.

  • If the Builder rejects or postpones the same, send him a legal notice through an advocate requesting for the same.
  • Even then if the builder refuses, File an application with the Registrar of Co-operative Societies together with all the relevant documents and 2000 Rs. Court stamp fees.
  • Self-attestation all the copies enclosed (by the society)
  • The Competent Authority will assess the application and if any documents are missing he will ask the applicant to correct the mistake within fifteen days.
  • Thereafter, notice would be sent to the promoter and the land owners.
  • After receipt of the notice by the land owners and the promoters, the authority will hear both parties in the first hearing and ask both parties to produce further evidences in next hearing.
  • Thereafter, second hearing would be held and if the builder or landowners do not attend both first and second hearing then the authority will pass an exparte order.
  • Thereafter, the third and final hearing would be held and the authority would be held and order would be passed unless a legal question is raised.
  • Normally the whole process is completed within a period of 6 months.

DOCUMENTS REQUIRED:

Further, the application required to be made with the Registrar shall be accompanied by copies of certain 20 odd documents which the society shall have to prepare or get prepared.

 

The papers required for doing Deemed Conveyance are as follows:

  • Application Form 7 to the District Deputy Registrar, Co-operative Societies, affixing a court fee stamp of Rs 2,000 on the application
  • Affidavit made before the Notary or Executive Magistrate True copy of the Society Registration Certificate
  • Stamp duty paid and registered agreement copy of 1 individual flats/ shops with Builder/Developer
  • List of members in prescribed format
  • Index-II for each member as issued by the Sub-Registrar of Assurance
  • Copy of the Development Agreement between land owner and builder
  • Copy of the Power of Attorney between land owner and builder
  • Copy of the legal notice issued to the original owner or developer for doing conveyance
  • Details of corresponding address telephone number etc. of the original owner or developer
  • Draft conveyance deed/ Declaration proposed to be executed in favour of the applicant

 

Documents to be obtained from City Survey Office, for submission:

  • City (CTS) Survey plan
  • Property Registration Card or
  • 7/12 extract of the land
  • Village form 6 (Mutation entries from Revenue Office)

 

Documents to be obtained from the Collector’s Office, for submission:

  • Copy of the Non-Agricultural Order
  • Certificate of the exclusion from Land Ceiling Act (ULC) Certificate

 

Documents to be obtained from the concerned Municipal Authority Office, for submission:

  • Copy of the approved plan
  • IOD
  • Commencement Certificate
  • Building Completion certificate
  • Occupation Certificate (not compulsory)
  • Property taxes paid
  • Location plan of the building

 

Documents to be obtained from other professionals, for submission:

  • Search Report of the land issued by the Solicitor/Advocate
  • Title Certificate of the Property issued by the Solicitor/Advocate (Search by minimum for last 30 years)
  • Land Measurement Map/ Architect’s Certificate (layout plan of the plot)
  • Certified copy from Panel Architect about the utilization of full FSI or FSI if any left in respect of the said property /Plot.

After, the Application is heard by the Registrar he may grant an order for deemed conveyance which shall then be produced before a court for execution and hence the conveyance may be done by a court order.

PROCEDURE:

Stage 1- Preparation for Deemed Conveyance
During this stage the Managing Committee prepares the Members of the Co- Operative Housing Society for Deemed Conveyance.

Stage 2- Documentation for Deemed Conveyance
During this stage the Documents Required for Deemed Conveyance are collected/ organized & the Case is prepared.

Stage 3- Legal Case for Deemed Conveyance
During this stage the case is filed before the Competent Authority & after contesting the same the Order & Certificate upholding the right of Deemed Conveyance of the Society is obtained.

Stage 4- Registration of Deemed Conveyance
During this stage the Deemed Conveyance Deed is Adjudicated, properly Stamped & Registered.

Stage 5- Transfer of Property after Deemed Conveyance
During this stage the Society Name is incorporated in the Land Revenue Records.

 

FOR MORE DETAILS CALL:

VED LEGAL,

Adv. Gajanan Rahate

Mob: 9763040088

E_mail: [email protected]

By |June 20th, 2018|PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE|Comments Off on PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

After the above mentioned conditions are fulfilled, the following steps shall be taken:

Write a letter /email to builder/ promoter requesting him to provide a draft of the SALE DEED/ CONVEYANCE DEED or providing the draft to him and requesting him to sign the same.

  • If the Builder rejects or postpones the same, send him a legal notice through an advocate requesting for the same.
  • Even then if the builder refuses, File an application with the Registrar of Co-operative Societies together with all the relevant documents and 2000 Rs. Court stamp fees.
  • Self-attestation all the copies enclosed (by the society)
  • The Competent Authority will assess the application and if any documents are missing he will ask the applicant to correct the mistake within fifteen days.
  • Thereafter, notice would be sent to the promoter and the land owners.
  • After receipt of the notice by the land owners and the promoters, the authority will hear both parties in the first hearing and ask both parties to produce further evidences in next hearing.
  • Thereafter, second hearing would be held and if the builder or landowners do not attend both first and second hearing then the authority will pass an exparte order.
  • Thereafter, the third and final hearing would be held and the authority would be held and order would be passed unless a legal question is raised.
  • Normally the whole process is completed within a period of 6 months.

DOCUMENTS REQUIRED:

Further, the application required to be made with the Registrar shall be accompanied by copies of certain 20 odd documents which the society shall have to prepare or get prepared.

 

The papers required for doing Deemed Conveyance are as follows:

  • Application Form 7 to the District Deputy Registrar, Co-operative Societies, affixing a court fee stamp of Rs 2,000 on the application
  • Affidavit made before the Notary or Executive Magistrate True copy of the Society Registration Certificate
  • Stamp duty paid and registered agreement copy of 1 individual flats/ shops with Builder/Developer
  • List of members in prescribed format
  • Index-II for each member as issued by the Sub-Registrar of Assurance
  • Copy of the Development Agreement between land owner and builder
  • Copy of the Power of Attorney between land owner and builder
  • Copy of the legal notice issued to the original owner or developer for doing conveyance
  • Details of corresponding address telephone number etc. of the original owner or developer
  • Draft conveyance deed/ Declaration proposed to be executed in favour of the applicant

 

Documents to be obtained from City Survey Office, for submission:

  • City (CTS) Survey plan
  • Property Registration Card or
  • 7/12 extract of the land
  • Village form 6 (Mutation entries from Revenue Office)

 

Documents to be obtained from the Collector’s Office, for submission:

  • Copy of the Non-Agricultural Order
  • Certificate of the exclusion from Land Ceiling Act (ULC) Certificate

 

Documents to be obtained from the concerned Municipal Authority Office, for submission:

  • Copy of the approved plan
  • IOD
  • Commencement Certificate
  • Building Completion certificate
  • Occupation Certificate (not compulsory)
  • Property taxes paid
  • Location plan of the building

 

Documents to be obtained from other professionals, for submission:

  • Search Report of the land issued by the Solicitor/Advocate
  • Title Certificate of the Property issued by the Solicitor/Advocate (Search by minimum for last 30 years)
  • Land Measurement Map/ Architect’s Certificate (layout plan of the plot)
  • Certified copy from Panel Architect about the utilization of full FSI or FSI if any left in respect of the said property /Plot.

After, the Application is heard by the Registrar he may grant an order for deemed conveyance which shall then be produced before a court for execution and hence the conveyance may be done by a court order.

PROCEDURE:

Stage 1- Preparation for Deemed Conveyance
During this stage the Managing Committee prepares the Members of the Co- Operative Housing Society for Deemed Conveyance.

Stage 2- Documentation for Deemed Conveyance
During this stage the Documents Required for Deemed Conveyance are collected/ organized & the Case is prepared.

Stage 3- Legal Case for Deemed Conveyance
During this stage the case is filed before the Competent Authority & after contesting the same the Order & Certificate upholding the right of Deemed Conveyance of the Society is obtained.

Stage 4- Registration of Deemed Conveyance
During this stage the Deemed Conveyance Deed is Adjudicated, properly Stamped & Registered.

Stage 5- Transfer of Property after Deemed Conveyance
During this stage the Society Name is incorporated in the Land Revenue Records.

 

FOR MORE DETAILS CALL:

VED LEGAL,

Adv. Gajanan Rahate

Mob: 9763040088

E_mail: [email protected]

By |June 18th, 2018|PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE|Comments Off on PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE

After the above mentioned conditions are fulfilled, the following steps shall be taken:

Write a letter /email to builder/ promoter requesting him to provide a draft of the SALE DEED/ CONVEYANCE DEED or providing the draft to him and requesting him to sign the same.

  • If the Builder rejects or postpones the same, send him a legal notice through an advocate requesting for the same.
  • Even then if the builder refuses, File an application with the Registrar of Co-operative Societies together with all the relevant documents and 2000 Rs. Court stamp fees.
  • Self-attestation all the copies enclosed (by the society)
  • The Competent Authority will assess the application and if any documents are missing he will ask the applicant to correct the mistake within fifteen days.
  • Thereafter, notice would be sent to the promoter and the land owners.
  • After receipt of the notice by the land owners and the promoters, the authority will hear both parties in the first hearing and ask both parties to produce further evidences in next hearing.
  • Thereafter, second hearing would be held and if the builder or landowners do not attend both first and second hearing then the authority will pass an exparte order.
  • Thereafter, the third and final hearing would be held and the authority would be held and order would be passed unless a legal question is raised.
  • Normally the whole process is completed within a period of 6 months.

DOCUMENTS REQUIRED:

Further, the application required to be made with the Registrar shall be accompanied by copies of certain 20 odd documents which the society shall have to prepare or get prepared.

 

The papers required for doing Deemed Conveyance are as follows:

  • Application Form 7 to the District Deputy Registrar, Co-operative Societies, affixing a court fee stamp of Rs 2,000 on the application
  • Affidavit made before the Notary or Executive Magistrate True copy of the Society Registration Certificate
  • Stamp duty paid and registered agreement copy of 1 individual flats/ shops with Builder/Developer
  • List of members in prescribed format
  • Index-II for each member as issued by the Sub-Registrar of Assurance
  • Copy of the Development Agreement between land owner and builder
  • Copy of the Power of Attorney between land owner and builder
  • Copy of the legal notice issued to the original owner or developer for doing conveyance
  • Details of corresponding address telephone number etc. of the original owner or developer
  • Draft conveyance deed/ Declaration proposed to be executed in favour of the applicant

 

Documents to be obtained from City Survey Office, for submission:

  • City (CTS) Survey plan
  • Property Registration Card or
  • 7/12 extract of the land
  • Village form 6 (Mutation entries from Revenue Office)

 

Documents to be obtained from the Collector’s Office, for submission:

  • Copy of the Non-Agricultural Order
  • Certificate of the exclusion from Land Ceiling Act (ULC) Certificate

 

Documents to be obtained from the concerned Municipal Authority Office, for submission:

  • Copy of the approved plan
  • IOD
  • Commencement Certificate
  • Building Completion certificate
  • Occupation Certificate (not compulsory)
  • Property taxes paid
  • Location plan of the building

 

Documents to be obtained from other professionals, for submission:

  • Search Report of the land issued by the Solicitor/Advocate
  • Title Certificate of the Property issued by the Solicitor/Advocate (Search by minimum for last 30 years)
  • Land Measurement Map/ Architect’s Certificate (layout plan of the plot)
  • Certified copy from Panel Architect about the utilization of full FSI or FSI if any left in respect of the said property /Plot.

After, the Application is heard by the Registrar he may grant an order for deemed conveyance which shall then be produced before a court for execution and hence the conveyance may be done by a court order.

PROCEDURE:

Stage 1- Preparation for Deemed Conveyance
During this stage the Managing Committee prepares the Members of the Co- Operative Housing Society for Deemed Conveyance.

Stage 2- Documentation for Deemed Conveyance
During this stage the Documents Required for Deemed Conveyance are collected/ organized & the Case is prepared.

Stage 3- Legal Case for Deemed Conveyance
During this stage the case is filed before the Competent Authority & after contesting the same the Order & Certificate upholding the right of Deemed Conveyance of the Society is obtained.

Stage 4- Registration of Deemed Conveyance
During this stage the Deemed Conveyance Deed is Adjudicated, properly Stamped & Registered.

Stage 5- Transfer of Property after Deemed Conveyance
During this stage the Society Name is incorporated in the Land Revenue Records.

 

FOR MORE DETAILS CALL:

VED LEGAL,

Adv. Gajanan Rahate

Mob: 9763040088

E_mail: [email protected]

By |June 6th, 2018|PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE|Comments Off on PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE