HANDOVER PROCESS WITH THE HELP OF BUILDER

HANDOVER PROCESS WITH THE HELP OF BUILDER

The date of handover from builder to the registered owners association is an important day for new apartment owners and all residents. It has to be taken seriously and detailed due diligence must bechina lesbian sex toys custom baseball jersey best nfl jerseys cheap lace front wigs best sex toys wig shop nike air max 97 mens adidas yeezy boost 700 adidas outlet online nfl shop coupon code nike air jordan 6 nfl dallas cowboys nfl fan shop best female sex toy nike air jordan sale done when interacting with the builders during this handover process. Once the formal handover to the Owners Association is completed, the onus is on the association to run the affairs of the society and to ensure its smooth functioning. The association must be prepared for this day for 3+ months leading to this event.

It is recommended that owners collaboratively engage with the builder right from late construction stages that will help them to take-up this responsibility in future. The builders can also reach out to representatives from the owners group to assist in the selection of maintenance agency which prepares them for the handover process.

Based on our experience in interacting with various builders and associations, we have collated a check list that associations can use when in dialogue with the builder on the handover process:

1. Get approved building plan which includes block-wise and floor-wise details

2. Collect the Completion Certificate which ensures adherence of the approved plan

3. No Objection certificates from pollution, fire, water and electricity authorities

4. Hard copy and soft copy (in CD) of all approved engineering drawings; look for approval seal on the drawings

5. Registration and parent documents

6. Drainage, sewage, Fire protection and common area power layout drawings

7. Car parking layout drawings (with numbering)

8. Asset Inventory of all movable and immovable equipment purchased; numbered in order (list needs to be exhaustive)

9. Record of recent service history on key equipment’s like lifts, DG sets, STP and WTP

10. AMC and warranty details; Original bills of equipment purchased (motors, Sewage and Water Treatment Plant, Generators, Gym items like treadmill)

11. Lift license details and next renewal date

12. STP/WTP vendor details, plant layout, operation manual and drawings

13. Receipts of property, electricity and water payments paid

14. Handover of corpus amount to the association

15. Share recent expenses incurred on various maintenance activities and account heads; will assist to budget coming year (staff salaries, purchase of cleaning material, swimming pool maintenance etc)

16.Contract signed with maintenance agency; agreed SLAs

17. Insurance taken for assets and third party lift insurance

18. Audited account statement at the time of handover 19. Arrange for introductory meeting with important suppliers and vendors

By |August 21st, 2023|HANDOVER PROCESS OF HOUSING SOCIETY FROM BUILDER OR CHIEF PROMOTER|Comments Off on HANDOVER PROCESS WITH THE HELP OF BUILDER

HANDOVER PROCESS WITH THE HELP OF BUILDER

HANDOVER PROCESS WITH THE HELP OF BUILDER

The date of handover from builder to the registered owners association is an important day for new apartment owners and all residents. It has to be taken seriously and detailed due diligence must be done when interacting with the builders during this handover process. Once the formal handover to the Owners Association is completed, the onus is on the association to run the affairs of the society and to ensure its smooth functioning. The association must be prepared for this day for 3+ months leading to this event.

It is recommended that owners collaboratively engage with the builder right from late construction stages that will help them to take-up this responsibility in future. The builders can also reach out to representatives from the owners group to assist in the selection of maintenance agency which prepares them for the handover process.

Based on our experience in interacting with various builders and associations, we have collated a check list that associations can use when in dialogue with the builder on the handover process:

1. Get approved building plan which includes block-wise and floor-wise details

2. Collect the Completion Certificate which ensures adherence of the approved plan

3. No Objection certificates from pollution, fire, water and electricity authorities

4. Hard copy and soft copy (in CD) of all approved engineering drawings; look for approval seal on the drawings

5. Registration and parent documents

6. Drainage, sewage, Fire protection and common area power layout drawings

7. Car parking layout drawings (with numbering)

8. Asset Inventory of all movable and immovable equipment purchased; numbered in order (list needs to be exhaustive)

9. Record of recent service history on key equipment’s like lifts, DG sets, STP and WTP

10. AMC and warranty details; Original bills of equipment purchased (motors, Sewage and Water Treatment Plant, Generators, Gym items like treadmill)

11. Lift license details and next renewal date

12. STP/WTP vendor details, plant layout, operation manual and drawings

13. Receipts of property, electricity and water payments paid

14. Handover of corpus amount to the association

15. Share recent expenses incurred on various maintenance activities and account heads; will assist to budget coming year (staff salaries, purchase of cleaning material, swimming pool maintenance etc)

16.Contract signed with maintenance agency; agreed SLAs

17. Insurance taken for assets and third party lift insurance

18. Audited account statement at the time of handover 19. Arrange for introductory meeting with important suppliers and vendors

By |April 28th, 2023|HANDOVER PROCESS OF HOUSING SOCIETY FROM BUILDER OR CHIEF PROMOTER|Comments Off on HANDOVER PROCESS WITH THE HELP OF BUILDER

HANDOVER PROCESS OF HOUSING SOCIETY FROM BUILDER OR CHIEF PROMOTER

The handover process of the society shall be completed within 3 months from the date of its registration along with all relevant document such as documents relating to project/scheme, society,accounts etc…by conducting first general meeting as per norms specified in Bye-laws.
Agenda of the first general body meeting should be as follows:-

First General Body Meeting obligatory Agenda (after registration):

• To elect a Chairman for the meeting
• To admit persons to membership who have applied for membership of the society.
• To elect a provisional Managing Committee
• To receive and approve the statement of account as prepared by the Chief Promoter of the society up to 14 days prior to the first general body meeting of the society.
• To authorize the committee to secure conveyance of right title and interest in the property in the name of the society from the promoter builder
• To impose restrictions on raising loan amount from outside
• To appoint internal auditor and to fix his remuneration
• To authorize one of the members of the provisional committee to call the first meeting of the provisional committee
• To take decision about taking membership of District Housing Federation and other institutions
• To give power to one member of provisional management committee to call meeting of the managing committee
• To consider the matters raised by the member except these matters which are necessary for giving advance notice with the permission of chairman and eleventh hour matter and to make resolution in that regard.