SOCIETY FORMATION AND HANDOVER PROCESS BY BUILDER

SOCIETY FORMATION AND HANDOVER PROCESS BY BUILDER

The Registration process and requirements are governed by Maharashtra State Co-operative Society Act 1960.

To Register Co-op. Housing Society, Minimum 10 member are required.

Less than 10 members Societies are also Registered as per M. S. Govt. Ordinance No. 1094 and 277/14 Dated 10/03/1995. But such member’s flats should be less than 700 Sq.ft. Carpet Area

As per M.S. Govt. Notification dated 24/07/1992 conditions for registrations are liberalized.
60 % of the Promoters are must be ready to form Co-op. Housing Society.
If flats are sold as per the Maharashtra Ownership Flats Act,1963 [MOFA] then it is the duty of the Builder / Developer to form society and hand over the Account + Documents to Provisional Working Committee [PWC] In this case the builder become CP and other flat owners become Promoters for Registration purpose. This society registers under Co-operation.
When the builder is not registering society due to some reasons or not support to registered society then flat purchasers can apply for registration of Co-operative Housing Society under Non Co-operation. In this case one of the flat owners should be elected as CP for Registration purpose. In this case some more time is taken to registered society as registrar is issue notice to builder for Non Co-operation. If no response then ex-party decision are taken for registration of the society. Now all the case of Non Co-operation Registration decisions is given by District Deputy Registrar [DDR] then society is registered
All flat owners should hold meeting and elect Promoter. All power for Registrations, documentation etc. should be given to promoter. The resolution should be passed and must be sign by all flat owners who wish to become member of the Co-operative Housing Society
Appoint Consultant / Legal Advocate for registration and ask him to comply all requirements. All members together also can do work for registration.
For registration of Co-op. Hsg. Society the following documents should be filed to Dy. Registrar / Asst. Registrar of Co-operative Department area concern in order as follow:
• Applications for Name to be reserved for Proposed Society’s
• Form of resolution electing a CP and Promoter and giving them authority for doing certain acts on behalf of the proposed society
• Notice to Builder
• Application form “A”
• Information in Annexure ” A ” ” B ” ” C ”
• Bye-Law of the Society 2 copies
• Details of Accounts Annexure ” D ”
• Bank Balance Certificate in Original
• Namuna 6
• Agreement of 1 Flat
• Advocate Search Report [Title Certificate]
• Society’s Building Plan
• Lay Out Plan
• Sanction Plan from Authority
• Commencement Certificate
• Completion Certificate
• Promoter’s Guarantee in form ” X ” On Rs. 100/- Stamp paper & notarized
• Guarantee in form” Y ” On Rs. 100/- Stamp paper & notarized
• Guarantee in form ” Z ” On Rs. 100/- Stamp paper & notarized
• Latest 7/12 or City Survey Revenue Record of Land [not more than 1 month old]
• Promoters Affidavit On Rs. 100/- Stamp paper & notarized
• Indemnity Bond On Rs. 500/- Stamp paper & notarized
• NA Order
• ULC Order
• Development Agreement and Power of Attorney
• List of Members in the society
• Scheme/Yojana Form
• Registration Fee Challan for Rs.2500
• Builder Non Co-operation form Z On Rs. 100/- Stamp paper & notarized if required 1 copy
On submission of above document the Dy./Asst. Registrar will go through the papers And document. If found OK he will make order for issue of Registration Certificate.
If any deficiencies are found then the applicant will be inform accordingly and documents will be corrected wherever necessary. When all papers are in order, he will issue order for issue of Registration Certificate.
Registration Certificate is issued with covering letter and Officer’s name is mentioned who will attend First General Meeting. Normally the Officer concern is not attending meeting. In absence, all members has to hold meeting and has to elect Provisional Working Committee [PWC] whose working period will be ONE Year.
After electing PWC the member of PWC has to submitted the M-20 bond on Rs. 100/- stamp paper with the sign of Officer’s whose name is in Covering latter to Dy./Asst. Registrar. All Rule and Regulations, resolution and minutes which is written in AGM Register must be sign by Officer’s name is mentioned in covering letter it is the most important step.[Many society forget this which create problem latter] After First Annual General Meeting PWC is replaced with new Working Committee [WC] whose working period will be FIVE Year. The new WC election can conduct before PWC time over with proper election process. WC also has to submitted the M-20 bond on Rs. 100/- stamp paper with the sign of election officer to Dy./Asst. Registrar.
When application for Name reservation of Society has given, the Dy./Asst. Registrar give instruction to Open Bank Account in Dist. Central Co-op. Bank The Account has to opened in the name of CP And deposit all money of Share Capital Contribution [per member Share Money is Rs. 50*10 = Rs. 500 i.e. 10 share of 50 rupees each] and Member ship Fees of Rs. 100/- i.e. Per member you have to deposit Rs. 600/- in bank and obtain Bank Balance Certificate and submitted it to Dy./Asst. Registrar. After First Annual General Body Meeting the Bank Account has to transfer in the name of Society.For bank Account operation Chairman sign must and either Secretary and Treasurer. Expenditure has to be made as per provision of Bye-Laws. Bank and Cash Transaction [Collection and Payment are handled by Treasure when Billing Clerk or Accountant are not been kept.

By |August 14th, 2020|SOCIETY FORMATION AND HANDOVER PROCESS BY BUILDER|Comments Off on SOCIETY FORMATION AND HANDOVER PROCESS BY BUILDER

LAWYERS FOR FORMATION OF A NEW HOUSING SOCIETY IN MUMBAI

LAWYERS FOR FORMATION OF A NEW HOUSING SOCIETY IN MUMBAI

First general body meeting (before registration)

In this meeting under Society’s Model Bye-law 3(iii), the Chief Promoter (could be the builder) is primarily selected by the promoters, who are members co-signing the registration application before the Registering Authority, under Bye-law 3(xii).

In this meeting, necessary resolutions are passed like opening the account in a bank in the name of proposed society and for obtaining permission for reserving the name of the society. It is compulsory for SRA/ MHADA recognized societies, for the first meeting to be video-recorded.

Application for registration

Normally, the name reservation proposal should be accompanied with the society resolutions and signatures of at least 10 Promoters who have attended the meeting. On allotment of name and permission to open a bank account by the Registrar, the Chief Promoter has to collect Share Capital, Entrance Fees from promoters and deposit the same in the branch of the bank permitted by the Registrar. It should be noted that the amount cannot be withdrawn from the Bank till the society is registered or its registration is refused, except with prior written permission of the Registrar. The Chief Promoter should submit registration proposal to the registering authority within a period of 3 months from the date of issue of Letter of Reservation in the name of the proposed society.

If builder/ promoter is not co-operating in registering the Co-operative Housing Society, then in that case, the application for registration of society be submitted in Form 6 (Rule 12) before the District Deputy Registrar, who has been given power under section 10(1) of the Maharashtra Ownership Flats Act 1963. While submitting the said proposal, a Notarized Indemnity Bond of the members who applied for the registration of society on the stamp paper of Rs. 200 is required.

Documents required for Registration
• 7/12 extract of the land or property card.
• Certificate concerning non-agricultural land from the competent authority
• The order of applicable or non-applicable of land ceiling Act
• Construction layout duly approved by the competent authority
• Letter of sanction for starting construction
• Certificate regarding completion of construction work
• Development Agreement if the land is taken for development
• Letter of Power of Attorney of the land
• Title search report of the land
• The registered agreement of purchases of the flat with necessary stamp duty paid
• Architect Certificate regarding construction
• List of Members
• Scheme of the Society
• Application for reserving name
• At least ten members are necessary for registration of society. On the other hand, the government has given permission subject to some conditions for the Housing society of fewer than 10 members by exercising powers. For registration proposal, the signature of sixty percent promoters, who participated in the registration proposal is necessary.
• If the land is given by the government or undertaking agency of the government then its guarantee letter.
• No objection certificates from the Charitable Commissioner if the land is of Trust.
• Certificate of the competent authority regarding non-agricultural plot
• While registering SRA/SRD and MHADA recognized Co-operative Housing Societies, it is obligatory to fulfill the necessary papers as per instructions are given by the authorities by their circulars in addition to above criterion.
• Application for Registering Society (A form)
• Table giving information of society (B Form)
• Table giving details of the members (C Form)
• Statement of Accounts of the Members (D Form)
• Notarized Guarantee letter by the Chief Promoter of the society on the stamp Paper of Rs. 100/-
• Notarized Guarantee letter by the Builder, Promoter on the Stamp Paper of Rs. 100/-
• Affidavit of Members (Affidavit of Minimum 10 Promoters)
• Two copies of bye-laws of the Society approved by the Commissioner, Co-operation and Registrar, Co-operative Societies and Maharashtra State, Pune
• Proof of the bank balance of the promoter member (deposit of each share of Rs. 500 and admission fee of Rs. 100), after getting permission for reservation in the District Central Co-operative Bank
• Challan of Rs. 2500/- deposited in the Government Treasury Registration fee for the Housing Society of the Backward class is Rs. 50/-
Approval by Registrar

It is the duty of the concerned Registrar to register the Co-operative Housing Society, by scrutinizing the proposal submitted after fulfillment of above mentioned documents, and shall make an arrangement of issuing certificate of registration society under Section 9(1) of the Maharashtra Co-operative Society Act 1960, and copy of the registered bye-law, memorandum regarding registration of society to the chief promoter. The order regarding registration of society should have been sent for publishing in government gazette to the Government Printing Press for appropriate action. It is necessary to take decision on the registration of the society within a period of two months from the date of the proposal of the society submitted to the Registrar.

If proposal of society registration is denied or no decision is taken within two months then it is necessary to send that proposal to the Divisional Joint Registrar, Co-operative Societies under Section 152 of the Maharashtra Co. operative societies Act, can be approached.

First General Body Meeting obligatory Agenda (after registration):

• To elect a Chairman for the meeting
• To admit persons to membership who have applied for membership of the society.
• To elect a provisional Managing Committee
• To receive and approve the statement of account as prepared by the Chief Promoter of the society up to 14 days prior to the first general body meeting of the society.
• To authorize the committee to secure conveyance of right title and interest in the property in the name of the society from the promoter builder
• To impose restrictions on raising loan amount from outside
• To appoint internal auditor and to fix his remuneration
• To authorize one of the members of the provisional committee to call the first meeting of the provisional committee
• To take decision about taking membership of District Housing Federation and other institutions
• To give power to one member of provisional management committee to call meeting of the managing committee
• To consider the matters raised by the member except these matters which are necessary for giving advance notice with the permission of chairman and eleventh hour matter and to make resolution in that regard.

By |August 14th, 2020|LAWYERS FOR FORMATION OF A NEW HOUSING SOCIETY IN MUMBAI|Comments Off on LAWYERS FOR FORMATION OF A NEW HOUSING SOCIETY IN MUMBAI

ADVOCATES FOR REGISTRATION OF HOUSING SOCIETY IN PUNE

ADVOCATES FOR REGISTRATION OF HOUSING SOCIETY IN PUNE:

A co-operative society is the perfect fit for a residential building as flat-owners have common needs (water connection, watchmen, etc) and interests (maintenance of common areas, such as the terrace and compound). If you’ve purchased a flat in a new building, it would probably be best if you took interest in forming a society. The builder may also be statutorily obligated to form a society. For example, under Maharashtra Flat Ownership Act, 1963, a builder must form a society within four months of selling 60% of the flats.
But you needn’t wait for the builder to form the society. In many states, including Delhi and Maharashtra, ten flat-owners are enough to promote a co-operative housing society. A building without a housing society usually indicates that there is a dispute between members or a general lack of interest. If you’re considering buying a house in a building where the society has not been formed, find out what the problem is. If the builder does not form a society, rights to the terrace and the compound continue to rest with him.
We, the “VED LEGAL” provide registration and formation services which help you at every step of society formation, right from inception to final handover. We look after all the legal complications involved in society formation and carry out necessary negotiations with developers.
We have also completed the registration process for various projects. We specialize in society formation of housing societies, commercial societies, maintenance societies and large townships. We help developers and societies with complex registration process during society mergers, society split, and federation registrations.
Our specialized services include:
• Initial screening
• Gap identification and ratification
• Process documentation and finalization
• Dispute resolution
• Society name reservation at respective co-operative departments
• Account formation and legal documentation
FOR MORE DETAILS CALL:
VED LEGAL,
Adv. Gajanan Rahate
Mob: 9763040088
E_mail: [email protected]

By |August 14th, 2020|ADVOCATES FOR REGISTRATION OF HOUSING SOCIETY PUNE|Comments Off on ADVOCATES FOR REGISTRATION OF HOUSING SOCIETY IN PUNE

MISGUIDING & MISLEADING WHATSAPP POST ABOUT SOCIETY’S CONVEYANCE DEED CANCELLATION:-

*MISGUIDING & MISLEADING WHATSAPP POST ABOUT SOCIETY’S CONVEYANCE DEED CANCELLATION:-

Now days, the Whatsapp post about the cancellation of society’s “Conveyance Deed” has been going viral speedily which is totally misleading & misguiding. And it’s really very painful to see that despite making the housing societies aware about their ownership/title of the land, someone stupid with incomplete source of knowledge is misguiding by circulating the baseless and support less post without verifying it’s lawful authenticity.

And due to this bullish and misleading viral post, a large number of the housing societies around us are getting confused that how to get cleared their title of the land, if Conveyance Deed is cancelled..?

Therefore, to avoid such confusion or mess and for the better or clear understanding, the housing societies and it’s members must go through the reliable source of knowledge which is given below in brief.

Now let’s understand what the cabinet decision talks about Property Card and ownership of the land (Conveyance Deed)…?

1. The original cabinet decision related to recording of ownership details of individual flat in Property card is of August 2019.

2. The Land Records are updated through mutation entries in Property Card in urban areas or through 7/12 Utara in Rural areas.

3. We can consider this as Horizontal Property Records. So basically these PR card entries are about the ownership of land/property.

4. What about ownership of Structure that is created on these lands??

5. The cabinet decision of August 2019 aims at first-ever initiative in India to record the ownership details of each and every flat, building and commercial complex.

6. So the cabinet decision is talking about a path breaking decision of updationof Vertical property records in the form of Supplementary PR cards.

7. This move is going to benefit to the home buyers who can trace the ownership of the flat through these Supplementary PR cards and satisfy themselves before buying the flat.

8. This move is beneficial for the financial institutions who are facing fraudulent transactions of multiple mortgages getting created against the same property.

9. This path breaking initiative will ensure that all the city survey offices in urban areas and the collector offices in rural areas will have records of the individual flats as well along with the land records.

10. Beware, that this cabinet decision is nothing to do with conveyance or deemed conveyance of the land* and hence conveyance is cancelled is fake and misleading.

11. The land owner/s has to convey the land in the name of the housing society and the builder/developer has to convey the title of building in the name of CHS and these are the provisions which are there in MOFA Act and RERA Act as well. So do not get misguided.

12. Your society still has to go for the conveyance because that is what your object clause says of the Model Bye laws.

13. The misleading information is circulated to create confusion and see to it that conveyance which is crucial for a CHS to get, will not be thought of and postponed by the CHS due to this baseless news, so please do not get misguided.

14. Conveyance provision is in MOFA Act, it is in MCS Act, it’s part of Model Bye laws, RERA Act and hence if it has to get cancelled then first al these acts needs to be amended.

15. So, friends please understand the implication of Conveyance, seek professional help on this, do not get carried away by the misleading post,do not circulate if you yourself are not sure.

Out of the all above – Important conclusion – is Housing Society’s Conveyance or Deemed Conveyance provision is not cancelled at all.

For detailed information please feel free to contact us.

Warm Regards,
Ved Legal,
Mob- 9763040088,
Email- [email protected]
Website- vedlegal.com

By |August 14th, 2020|MISGUIDING & MISLEADING WHATSAPP POST ABOUT SOCIETY'S CONVEYANCE DEED CANCELLATION|Comments Off on MISGUIDING & MISLEADING WHATSAPP POST ABOUT SOCIETY’S CONVEYANCE DEED CANCELLATION:-

EASY PROCEDURE OF DEEMED CONVEYANCE IN PUNE

EASY PROCEDURE OF DEEMED CONVEYANCE IN PUNE

The Maharashtra government has relaxed the terms for the deemed conveyance (DC)-ownership right of plot certificate from the builder, by bringing down the number of documents required from 12 to 8 and stipulating that DC will be given even if the society does not have an Occupation Certificate (OC) or the Building Completion Certificate (CC).
It is mandatory for land-owners or developers to convey the title of the plot within four months of the formation of the housing society. In many cases, the builders fail to convey the title of properties to the housing societies, in the hope of availing more floor space index (FSI) that may become available in future, or to avail the benefits accrued to them in case the property is redeveloped.

If the builder fails to convey the property, the Maharashtra Ownership Flats Act (MOFA) allows societies to apply for DC. However, having OC was mandatory and was insisted upon by the officials of the cooperative registrar’s office. OC is given only when the building is complete in all respects and has complied with the mandatory norms laid down by the government authorities to make it ready for occupation. Since most of the builders abandon the projects before complying with the norms and conditions, OCs are not given to the societies. Developers just hand over the possession and exit the project, leaving the residents high and dry.

However now, the DC will be issued even if housing societies have submitted such documentary evidence as the formation of the society or the payment of property tax by the society.

As per the GR issued on 22 June 2018, by the state cooperation department, it has been made mandatory for the registrar of cooperative societies to register documents of the applicants within a day. Besides, as per the Maharashtra Right to Public Services Act, 2015, the DC should be issued within six months. If an official fails to provide and approve it within the prescribed period, then he or she will be penalized between Rs500 and Rs.5,000/-
The applicants should submit the applications with a court fee of Rs2,000. In case the FSI has already been consumed, a certificate of an architect that the total FSI has been consumed would suffice. In addition, they have to give an indemnity bond stating that they will take responsibility for the building and adhere to all required rules and regulations. If there are more than one society on one plot, the details of proportionate area and ground coverage should be furnished.

The documents required for conveyance include society registration certificate, approved layout, 7/12 extract, sale deed of each flat owner or heir document, list of registered members of the society, occupation certificate, non-agriculture certificate of that particular plot and notice copy etc. In the absence of sale deeds of all members, the sale deed of even one member would be sufficient, states the GR.

While submitting the conveyance application and documents to the registrar, a copy of the same application also needs to be submitted to the stamp duty and registration department for its speedy approval. The applications will be accepted online as well as offline. The officials of the concerned department such as urban, cooperative, forest and revenue department will have to work in unison so that the applicants are not required to shuttle from one department to another.

The system of issuing DC was started three years ago. However, due to stringent conditions there was no response from cooperative societies. Commenting on the issue, Ramesh Prabhu, Chairman, Maharashtra Societies Welfare Association said “This was a positive step. In many cases, the builders exited the project without getting the OC, and the residents had to bear the brunt. This relaxation will ensure that majority of the societies get deemed conveyance. By a fair estimate over 10,000 cooperative housing societies in Mumbai and neighboring areas, are yet to get the DC. Now they should come forward to take advantage of these relaxed norms.”

There are a sizable number of housing societies in Mumbai that are struggling to get the DC. In absence of DC, redevelopment of some of the societies has been delayed. Some of the developers used to sell the flats till they held the ownership right of the layout and were misusing this right, causing impediment in the way of redevelopment.

By |August 14th, 2020|EASY PROCEDURE OF DEEMED CONVEYANCE IN PUNE|Comments Off on EASY PROCEDURE OF DEEMED CONVEYANCE IN PUNE

Essential Elements in a Conveyance Deed

Essential Elements in a Conveyance Deed

The term “Deed” means a written legal contract that binds the parties to its terms and can be proved in the court as evidence.
The term ‘Conveyance’ is used when there is transfer of ownership or legal title in a property from one person to another. Hence, a conveyance deed is a legal document between a transferor and a transferee, which proves that a title or ownership in the property along with all other rights related to the property have been transferred from one person to another.
It informs that the property is free from any restrictions and disputes. Both parties sign it and it can be produced in a court if any dispute relating to the agreement arises in future.
However, a conveyance deed is a wide term which not only includes a sale of the property but also other kinds of transfers such as gift, exchange, lease, mortgage, relinquishment and other transfers.
A conveyance deed is valid only when the property is sold for a valid consideration (usually money) except in the case of a gift deed which results out of love and affection.
It can be signed for either movable or immovable property.
A conveyance deed is executed in accordance with the legal provisions under the Transfer of Property Act 1882, Registration Act 1908 and Indian Stamp Act, 1899.
In order to be valid and acceptable in a court, a conveyance deed needs to contain some essential elements. For instance, it must:
* Establish exact boundaries of the property to avoid any dispute relating to land ownership,
* State that all the rights relating to the property have been transferred along with the property,
* Provide details regarding delivery and acceptance of the property,
* State all terms and conditions relating to the transfer,
* Be made on a non-judicial stamp paper and signed by both parties,
* Mention full names, addresses and other requisite details of the seller and the buyer,
* State that the property is free from any disputes and restrictions,
* Be signed by at least two witnesses
* Be in writing and notarized, and
* Be registered through the local registrar’s office by submitting appropriate registration fee. Registration is proof that the property is free from any disputes and has been transferred to the buyer permanently with a clean title.
Once the registration is complete, the buyer becomes the absolute owner of the property and the conveyance process gets over officially. A lawyer and a real estate agent can help two parties compose, sign, and register a deed of conveyance during a transaction. The government obtains its revenue from the stamp duty and registration fees.

By |August 14th, 2020|Essential Elements in a Conveyance Deed|Comments Off on Essential Elements in a Conveyance Deed

Need for Deemed Conveyance in Mumbai

Need for Deemed Conveyance in Mumbai

A Co-Operative Housing Society is the owner of the Land & Building & individual member enjoys the ownership right of the Flat/ Shop based on the Share Certificate issued by the Co- Operative Housing Society.

A vast majority of Co- Operative Housing Societies does not have the Conveyance in their favour& hence are not the owners of their Land & Building. In this situation, even though each member of the Co- Operative Housing Society has paid full consideration and is in possession of the Flat/ Shop allotted, he does not enjoy the benefits of title ownership of the Flat/ Shop.
In case of Co-Operative Housing Societies formed long back, many of the Buildings are in dilapidated condition and their repairs are not economically viable. The best solution available for these Co- Operative Housing Societies is to go ahead with Redevelopment. The non- availability of the Conveyance & therefore free/ marketable Title affects the Redevelopment Process badly.
In case of Co- Operative Housing Societies formed recently, the Redevelopment at the moment is not on the agenda. However the non- availability of the Conveyance and free and marketable Title may affect its present Revenue and may be a hindrance in Redevelopment process in future.
Therefore Deemed Conveyance is in the larger interest of the Co- Operative Housing Societies (and their each and every member) who are denied their right of Conveyance by the Land- Owners & Property Developers.

By |August 14th, 2020|Need for Deemed Conveyance in Mumbai|Comments Off on Need for Deemed Conveyance in Mumbai

Documentation for Deemed Conveyance

Documentation for Deemed Conveyance

Documentation is a very important & crucial stage in the Procedure for Deemed Conveyance. It requires absolute focus & meticulous handling to ensure that all the required documents are obtained & organized in an appropriate manner.
The Land Revenue Records of recent origin are obtained by making applications to the respective Government Departments like City Survey Office, Tahasildar/ Talathi Office & District Collector Office. These documents are obtained typically within 8- 10 weeks.
The Municipal Corporation Records are obtained by making application to the Building Proposal Department of the Municipal Corporation. These documents are obtained typically within 8- 10 weeks.
In case it is difficult to obtain the Land Revenue Records & Municipal Corporation Records, Right to Information (RTI) may be invoked.
The Society Records are obtained from Society Office & the Professional Certificates are obtained from Professionals.
Following Documents are required to be prepared.
 Deemed Conveyance Application- Form VII
 Synopsis of the Case
 Vakalatnama
 Roznama
 Society Special General Body Resolution
 Letter of Authority
 Affidavit by Authorised Representative
 Affidavit by Society Secretary
 List of Society Members including their Flat/ Shop Agreement Details
During the Documentation Stage, a Legal Notice is to be sent to the Land Owners & Property developers.
The complete set of the above Documents is to be annexed with the Deemed Conveyance Application- Form VII & to be filed in a neat & tidy manner.
The complete Deemed Conveyance Application- Form VII is to submitted to the Competent Authority- The District Deputy Registrar of Co- Operative Societies of the particular District.
The Documentation Stage from beginning to submission of Deemed Conveyance Application- Form VII can be successfully completed within 90 to 120 days.

By |August 14th, 2020|Documentation for Deemed Conveyance|Comments Off on Documentation for Deemed Conveyance

Registration of Deemed Conveyance in Thane

Registration of Deemed Conveyance in Thane

On receipt of the Deemed Conveyance Order, the Deemed Conveyance Deed between the Competent Authority & the Society is prepared. The Competent Authority appears in the Deed on behalf of the defaulting Land Owners & Property Developers.
The Deemed Conveyance Deed is submitted to the Office of Competent Authority for Approval & their Signature with Authority Stamp & Seal.
The Special General Body of the Society is called to approve the Deemed Conveyance Deed & to nominate 3 Members of the Society to sign the Deed.
The Deemed Conveyance Deed is executed by the signature of the Competent Authority & the signatures of the 3 nominated Members of the Society.
On execution of the Deemed Conveyance Deed, it is forwarded to the District Stamp Office for Adjudication. If all the Members of the Society have paid the Stamp Duty on their respective Flat/ Shop Agreements & there is no balance FSI, the Deemed Conveyance Deed attracts only Rs. 100/- Stamp Duty. The Stamp Office issues the Adjudication Certificate.
On receipt of the Adjudication Certificate, the Society pays the required Stamp Duty & gets the Deemed Conveyance Deed Franked from local Bank.
After Franking of the Deemed Conveyance Deed, the same is submitted to the Registration Office for Registration. The Registration Office issues a notice to the Land Owners & Property Developers to verify whether they have received any Stay Order from Proper Court against the Deemed Conveyance Order.
The Proper Court for issuing the Stay Order against the Deemed Conveyance Order is High Court. It is very difficult for the Land Owners & Property Developers to obtain the Stay Order from High Court against the Deemed Conveyance Order.
If there is no Stay Order received, the Registration Office Registers the Deemed Conveyance Deed. The Competent Authority is exempted from appearing for the Registration & hence the 3 Members nominated by the Society only appear for Registration.
After Registration of the Deemed Conveyance Deed, the Registration Office issues the Scanned Document & Index II typically within 15 days.
The complete Procedure of Registration of Deemed Conveyance Deed is typically completed within 3- 4 Months.
On receipt of the Index II, the Registration Process of the Deemed Conveyance Deed is successfully completed & the Society becomes the owner of the Land & Structure.

By |August 14th, 2020|Registration of Deemed Conveyance in Thane|Comments Off on Registration of Deemed Conveyance in Thane

PROVISIONS FOR DEEMED CONVEYANCE UNDER MOFA

PROVISIONS FOR DEEMED CONVEYANCE UNDER MOFA

Amendments in Maharashtra Ownership Flats (Regulation of the promotion of construction, sale, management and transfer) Act, 2005 giving a huge relief to hundreds and thousands of flats purchasers in Maharashtra. Conveyance to the societies was a burning issues which have integrated many problems like property tax, housing finance documentations and major repairs or redevelopment.

The highlights of the amendments are as under:
• Builder/s will have to execute the conveyance.
Power is given to the District Deputy Registrar to act as Competent Authority. (Sec. 5A)
• Power is given to Competent Authority for registration of Co-operative Society under the provisions of Maharashtra Co-operative Societies Act, 1960. (Sec. 10(1) )
• It is the duty of the promoter (builder) to file with the Competent Authority within the prescribed period a copy of the conveyance executed by him (Sec. 11(2))
• If the promoter fails to execute the conveyance in favour of Co-operative Society, Company or Associations or Apartment Owners as the case may be, then the flat purchasers can approach the Competent Authority with true copy of registered agreement of all the flat purchasers including Occupation Certificate, Registration Certificate of the society then in such circumstances the Co-operative Society, Company or Associations is entitled to have unilateral deemed conveyance (Sec. 11(3))
• The proceedings before the Competent Authority have to be completed within a period of 6 months. The Competent Authority must verify the authenticity of the document produced before him and after giving a reasonable opportunity to the promoter, if satisfied will issue a certificate to the Sub-Registrar or any other Registration Officer under the Registration Act, 1908, certifying that it is a fit case for enforcing unilateral execution of conveyance deed conveying the right, title and interest of the promoter in the land and the building in favour of the applicant, as deemed conveyance(Sec. 11(4))
• The sub registrar after receipt of the certificate issued by the Competent Authority along with the unilateral instrument of conveyance can issue summons to the promoter to show cause why the unilateral instrument should not be registered as deemed conveyance. However, reasonable opportunity of being heard may be given to the promoter. If the Sub-Registrar is satisfied then he will register the unilateral conveyance as ‘deemed conveyance’. (Sec. 11(5))
• The Competent Authority has been created who has powers to award criminal imprisonment to the builder/s for a period not less than 6 months and not more than 1 year and / or along with fine ranging from Rs 10,000/- to 50,000/- (Sec. 13(3)(a) & 13(3)(b))
• The builder/s if convicted will not be able to carry on construction activities for a period of five years. However, the disqualification shall not affect the permission for construction of flats already granted. (Sec. 13 (4), 13(5) & 13(6) )
• The Competent Authority shall be deemed to be a public servant as per the provisions of Indian Penal Code. (Sec. (13B)
• Proceedings before Competent Authority shall be aimed to be judicial proceedings as per the provisions of Indian Penal Code. (Sec. 13C)
• Competent Authority shall be deemed to be a Civil Court for certain purposes. (Sec. 13D)
• No action can be taken against the Competent Authority for acts done in good faith by the Competent Authority. (Sec. 13E)

By |August 14th, 2020|PROVISIONS FOR DEEMED CONVEYANCE UNDER MOFA|Comments Off on PROVISIONS FOR DEEMED CONVEYANCE UNDER MOFA