­

ADVOCATES FOR REGISTRATION OF HOUSING SOCIETY:

ADVOCATES FOR REGISTRATION OF HOUSING SOCIETY:

A co-operative society is the perfect fit for a residential building as flat-owners have common needs (water connection, watchmen, etc) and interests (maintenance of common areas, such as the terrace and compound). If you’ve purchased a flat in a new building, it would probably be best if you took interest in forming a society. The builder may also be statutorily obligated to form a society. For example, under Maharashtra Flat Ownership Act, 1963, a builder must form a society within four months of selling 60% of the flats.

But you needn’t wait for the builder to form the society. In many states, including Delhi and Maharashtra, ten flat-owners are enough to promote a co-operative housing society. A building without a housing society usually indicates that there is a dispute between members or a general lack of interest. If you’re considering buying a house in a building where the society has not been formed, find out what the problem is. If the builder does not form a society, rights to the terrace and the compound continue to rest with him.

We, the “VED LEGAL” provide registration and formation services which help you at every step of society formation, right from inception to final handover. We look after all the legal complications involved in society formation and carry out necessary negotiations with developers.

We have also completed the registration process for various projects. We specialize in society formation of housing societies, commercial societies, maintenance societies and large townships. We help developers and societies with complex registration process during society mergers, society split, and federation registrations.
Our specialized services include:

• Initial screening
• Gap identification and ratification
• Process documentation and finalization
• Dispute resolution
• Society name reservation at respective co-operative departments
• Account formation and legal documentation
FOR MORE DETAILS CALL:
VED LEGAL,
Adv. Gajanan Rahate
Mob: 9763040088
E_mail: [email protected]

By |November 12th, 2018|ADVOCATES FOR REGISTRATION OF HOUSING SOCIETY|Comments Off on ADVOCATES FOR REGISTRATION OF HOUSING SOCIETY:

CONVEYANCE SERVICES FOR SOCIETIES:-

CONVEYANCE SERVICES FOR SOCIETIES:-

In most of the cases people believe that a Purchase Agreement is the final document they need to own. However, a mere purchase agreement does not pass on the developer’s rights on the land to the society. Societies need to make sure they have the complete right to the land, and mere society registration and formation does not provide those rights.
A Conveyance Deed helps societies to gain the right of their land. Post this builder relinquishes his legal right on the land.
We the “VED LEGAL” provide end-to-end conveyance services to the societies including execution of Conveyance Deed, Deemed Conveyance, and Deed of Apartments. We work closely with co-operative societies and government officials and make sure the complete process is hassle free.
With our team of legal advisers and professional approach, we have handled more than 100 cases across Pune. We guide our clients through the complete process of transferring builder’s rights, allocation of additional space and finally establishment of society rights, as per the law.
Our conveyance services include:
Apartment formation:
• Deed of Declaration • Deed of Apartment
Co-operative Societies Conveyance:
• Conveyance deed with builder’s consent • Deemed Conveyance – without builder’s consent

By |November 12th, 2018|Conveyance Services for Societies|Comments Off on CONVEYANCE SERVICES FOR SOCIETIES:-

A COMPLETE GUIDE TO DEEMED CONVEYANCE

A COMPLETE GUIDE TO DEEMED CONVEYANCE

Most of the flat-owners of the newly constructed Societies/apartments do not have their sale deeds or conveyance deeds. Mostly in the newly constructed buildings, the builders provide for forming a housing co-operative society to which they shall transfer their interest in the property. Then the builders form the society but do not transfer the title of the property (read ownership) to the flat-owners or the society till he has transferred all the rights in the building/ Societies/apartments. Thus the builders/promoters are benefiting from the buyers lack of awareness and information.
To curb this practice, amendments were carried out in the Maharashtra Ownership Flats Act, 1963, in 2008 to appoint a Competent Authority (Registrar of Co-operative Housing Societies) to hear the grievances of such Societies/apartments owners and to safeguard their interest by executing deemed conveyance of such societies u/s 11(3) of Maharashtra Ownership Flats Act, 1963.
Ved Legal is having enough experience to deal with these kinds of Deemed Conveyance of Co-operative Housing Societies, in and around pune. Any aggrieved society or apartment holder can get resolution from us in regards of the same.

MEANING OF DEEMED CONVEYANCE:
A deemed conveyance means when the builder/ promoter/ developer of the project refuses to sign the conveyance deed the court can sign the same on behalf of the builder and record the same in the government records.

NEED FOR DEEMED CONVEYANCE:
In a situation when a promoter or owner of residential premises/ buildings does not transfer/convey the ownership of the flats to the housing society or association of persons (AOP), the society or AOP can make an application to Registrar of Co-operative Housing Societies, to transfer the ownership of the said flats to them. This process is carried on through Deemed Conveyance of the title of the buildings and land in favour of the Society or AOP without the need of the builder to do so.

IMPORTANCE AND PROVISIONS OF LAW ON CONVEYANCE:
As per the Housing Society bye-laws, the main objective of formation of the Society is to obtain the Conveyance; and if Conveyance is not given by the Builder within four months from the date of registration of the Society, a case can be filed against the Builder to obtain the Conveyance. As per Section 13 of Maharashtra Ownership Flats Act, 1963, failure to give Conveyance is an offence and the Builder can be imprisoned up to 3 years or fined or both.

ADVANTAGES OF CONVEYANCE:
1. Getting a proper and legal title in the name of the Society.
2. Retaining the additional FSI as per the Government announcements.
3. Property will be free and marketable.
4. Society can raise the loans for repairs and reconstruction by mortgage.
5. Permission from planning authorities is possible if the building has to be reconstructed at a later date due to dilapidation of the structure due to age or by earthquake.
6. Society can take the benefit of TDR.
7. Members can receive compensation from Builder on redevelopment of the building.
DISADVANTAGES OF NOT HAVING CONVEYANCE DEED
Even though you have purchased ownership flat, you are not the owner of the land and building. 2. In the event of a building collapse or damage to the building, you cannot reconstruct the building without the permission of the Builder / Land owner.
1. The Builder/Developer may mortgage the property purchased by you as he is the legal owner and holding the Title Deeds of the Property.
2. The Builder/Developer may tap the benefits in case the building is later taken up for redevelopment or if the plot has some unutilized floor space index.
3. The Builder may make profit by sale of open spaces, gardens, terrace, parking space belonging to the Society.
4. The Builder may demand a huge amount from the Society, if Conveyance is sought by the Society after a lapse of many years.
5. The Builder may sell the entire Development Rights and the Legal Rights on the land to third party and create a third party interest in the Property and the Society will have to incur a huge amount to clear the same.
CONDITIONS PRECEDENT FOR GETTING A DEEMED CONVEYANCE:
There are certain important conditions which need to be fulfilled to go ahead for deemed conveyance, some of them are:

1. At least 60% of the flats in that scheme should be sold.
2. A Co-operative Society or Association of Persons should have been formed of the flat-owners and at least 3-4 months should have been passed since then.
3. There should be communication between the builder and the society or AOP regarding Deemed Conveyance wherein the builder should have made a promise of completion of conveyance or refused to do the same.

PROCEDURE FOR FILING AN APPLICATION FOR DEEMED CONVEYANCE:
After the above mentioned conditions are fulfilled, the following steps shall be taken:
Write a letter /email to builder/ promoter requesting him to provide a draft of the SALE DEED/ CONVEYANCE DEED or providing the draft to him and requesting him to sign the same.
• If the Builder rejects or postpones the same, send him a legal notice through an advocate requesting for the same.
• Even then if the builder refuses, File an application with the Registrar of Co-operative Societies together with all the relevant documents and 2000 Rs. Court stamp fees.
• Self-attestation all the copies enclosed (by the society)
• The Competent Authority will assess the application and if any documents are missing he will ask the applicant to correct the mistake within fifteen days.
• Thereafter, notice would be sent to the promoter and the land owners.
• After receipt of the notice by the land owners and the promoters, the authority will hear both parties in the first hearing and ask both parties to produce further evidences in next hearing.
• Thereafter, second hearing would be held and if the builder or landowners do not attend both first and second hearing then the authority will pass an exparte order.
• Thereafter, the third and final hearing would be held and the authority would be held and order would be passed unless a legal question is raised.
• Normally the whole process is completed within a period of 6 months.
DOCUMENTS REQUIRED:
Further, the application required to be made with the Registrar shall be accompanied by copies of certain 20 odd documents which the society shall have to prepare or get prepared.

The papers required for doing Deemed Conveyance are as follows:
o Application Form 7 to the District Deputy Registrar, Co-operative Societies, affixing a court fee stamp of Rs 2,000 on the application
o Affidavit made before the Notary or Executive Magistrate True copy of the Society Registration Certificate
o Stamp duty paid and registered agreement copy of 1 individual flats/ shops with Builder/Developer
o List of members in prescribed format
o Index-II for each member as issued by the Sub-Registrar of Assurance
o Copy of the Development Agreement between land owner and builder
o Copy of the Power of Attorney between land owner and builder
o Copy of the legal notice issued to the original owner or developer for doing conveyance
o Details of corresponding address telephone number etc. of the original owner or developer
o Draft conveyance deed/ Declaration proposed to be executed in favour of the applicant

Documents to be obtained from City Survey Office, for submission:
o City (CTS) Survey plan
o Property Registration Card or
o 7/12 extract of the land
o Village form 6 (Mutation entries from Revenue Office)

Documents to be obtained from the Collector’s Office, for submission:
o Copy of the Non-Agricultural Order
o Certificate of the exclusion from Land Ceiling Act (ULC) Certificate

Documents to be obtained from the concerned Municipal Authority Office, for submission:
o Copy of the approved plan
o IOD
o Commencement Certificate
o Building Completion certificate
o Occupation Certificate (not compulsory)
o Property taxes paid
o Location plan of the building

Documents to be obtained from other professionals, for submission:
o Search Report of the land issued by the Solicitor/Advocate
o Title Certificate of the Property issued by the Solicitor/Advocate (Search by minimum for last 30 years)
o Land Measurement Map/ Architect’s Certificate (layout plan of the plot)
o Certified copy from Panel Architect about the utilization of full FSI or FSI if any left in respect of the said property /Plot.
After, the Application is heard by the Registrar he may grant an order for deemed conveyance which shall then be produced before a court for execution and hence the conveyance may be done by a court order.
PROCEDURE:
Stage 1- Preparation for Deemed Conveyance
During this stage the Managing Committee prepares the Members of the Co- Operative Housing Society for Deemed Conveyance.
Stage 2- Documentation for Deemed Conveyance
During this stage the Documents Required for Deemed Conveyance are collected/ organized & the Case is prepared.
Stage 3- Legal Case for Deemed Conveyance
During this stage the case is filed before the Competent Authority & after contesting the same the Order & Certificate upholding the right of Deemed Conveyance of the Society is obtained.
Stage 4- Registration of Deemed Conveyance
During this stage the Deemed Conveyance Deed is Adjudicated, properly Stamped & Registered.
Stage 5- Transfer of Property after Deemed Conveyance
During this stage the Society Name is incorporated in the Land Revenue Records.
Let’s discuss each step in detail:

1. Preparation for Deemed Conveyance:
In this stage the managing committee needs to pass resolution to undergo deemed conveyance. A Special General Meeting is scheduled with prior notification and consent of all the members is obtained to move ahead.

During this SGM the following Resolutions are typically passed.
1. Resolution for going ahead with Deemed Conveyance
2. Resolution for Appointment of Authorized Representative
3. Resolution for Appointment of Legal Consultant for Deemed Conveyance
4. Resolution for Per Member Contributions
2. Documentation for Deemed Conveyance:
This is the most crucial step in obtaining deemed conveyance. It is a very meticulous job and make sure all the documents are lined up within the right format. You would require land revenue records, municipal corporation records, society records, property development records and professional certificates.
All these documents can be obtained from various departments such as Land revenue records from City Survey Office, Tahasildar/Talathi Office & District Collector Office, municipal corporation records from Building Proposal Department of the Municipal Corporation. Society records and certificates can be obtained from society offices and professionals.
Once all the documents are lined up, society needs to fill in Deemed Conveyance Application- Form VII and attached all the related documents. In case of deemed conveyance, a legal notice is sent to the developer for their consent. In regular conveyance procedures, since the developers or promoters are willingly providing the rights lot of documents can be easily recovered from them.
Once the form is filled up and all documents are annexed it is submitted to the Competent Authority- the District Deputy Registrar of Co- Operative Societies of the particular District.
3. Legal Case for deemed conveyance:
Once the application is submitted to the authorities they issue Deemed Conveyance Scrutiny Report- Form VIII within 1 month. Once the compliance is provided the authorities issues Summons & Newspaper Notices to the Land Owners & Property Developers for appearing for the hearing.
During the hearing process authorities take into consideration the arguments of the both parties. The process takes place within 3-4 months. Once all the arguments are documented the office issues a Deemed Conveyance order within 1 month. The whole process is completed within 6 months as this is a time bound activity.
4. Registration of deemed conveyance:
A deemed conveyance deed is created during this phase and is signed by both societies and developers. If developers do not appear for hearing in the prior stage (Which is the case in deemed conveyance), authorities have the power to sign the deed on behalf of developers.
The society needs to conduct a meeting and appoint 3 members to sign the deed. Post that the deed is submitted to district stamp office for adjudication. If all the members have paid their stamp duty and if there is no balance FSI, the office issues adjudication certificate. (Note – Deed only requires Rs 100 stamp duty). The adjudication certificate needs to be then franked from local bank and resubmitted to registration office.
The registration office then issues notice to land owner/developer to verify if there is any stay order against the deed of conveyance. (Note – The developer can get the stay order only from high court). If there is no stay order the deed of deemed conveyance is registered and then the office issues scanned documents and Index II. This mark end of registration process and the society becomes the owner of the land and structure.
5. Transfer of property:
In this phase a new application is submitted to various departments to make mutation entries in their records. This would make the process complete.
FOR MORE DETAILS CALL:
VED LEGAL,
Adv. Gajanan Rahate
Mob: 9763040088
E_mail: [email protected]

By |November 12th, 2018|A complete guide to Deemed Conveyance|Comments Off on A COMPLETE GUIDE TO DEEMED CONVEYANCE

PROCEDURE FOR REGISTRATION OF CO-OP. SOCIETIES

1.The first Step is to get 10 Individuals together who are desirous of forming a Society.
2.A Provisional Committee should be formed and a chief Promoter should be elected from amongst them.
3.A Name for the Society has to be selected.
4.An Application has to be made to the Registration Authority for reservation of Name and a letter to that effect has to be obtained confirming the reservation of Name. The name once reserved is valid for 3 Months.
5.The entrance fees and share capital has to be collected from the prospective members.
6.A Bank account has to be opened in the name of the proposed society as per the directions of the registration Authority. The entrance fees and share money has to be deposited in the bank account and the certificate from the bank has to be obtained in that respect.
7.The registration fees has to be deposited with the Reserve Bank of India and receipted 1challan thereof is to be obtained.
8.The application for registration of the society should be submitted to the Registrar of Societies of the concerned municipal ward. The documents to be submitted for registration are as follows:
a. Form No. A in quadruplicate signed by 90% of the promoter members
b. List of promoter members
c. Bank Certificate
d. Detailed explanation of working of the society.
e. 4 copies of proposed bye-laws of the society.
f. Proof of payment of registration charges.
g. Other documents like affidavits, indemnity bonds, any documents specified by the Registrar also have to be submitted.
9.The Registrar will enter the particulars in register of application maintained in Form “B” and give serial number and issue receipt in acknowledgment of the same.
10.On registration, the Registrar will notify the registration of the Society in the Official Gazette and issue Registration Certificate.

By |November 10th, 2018|PROCEDURE FOR REGISTRATION OF CO-OP. SOCIETIES|Comments Off on PROCEDURE FOR REGISTRATION OF CO-OP. SOCIETIES

SOCIETY FORMATION AND HANDOVER PROCESS BY BUILDER

The Registration process and requirements are governed by Maharashtra State Co-operative Society Act 1960.

To Register Co-op. Housing Society, Minimum 10 member are required.

Less than 10 members Societies are also Registered as per M.S.Govt. Ordinance No. 1094 and 277/14 Dated 10/03/1995. But such member’s flats should be less than 700 Sq.ft. Carpet Area

As per M.S. Govt. Notification dated 24/07/1992 conditions for registrations are liberalized.
60 % of the Promoters are must be ready to form Co-op. Housing Society.
If flats are sold as per the Maharashtra Ownership Flats Act,1963 [MOFA] then it is the duty of the Builder / Developer to form society and hand over the Account + Documents to Provisional Working Committee [PWC] In this case the builder become CP and other flat owners become Promoters for Registration purpose. This society registers under Co-operation.
When the builder is not registering society due to some reasons or not support to registered society then flat purchasers can apply for registration of Co-operative Housing Society under Non Co-operation. In this case one of the flat owners should be elected as CP for Registration purpose. In this case some more time is taken to registered society as registrar is issue notice to builder for Non Co-operation. If no response then ex-party decision are taken for registration of the society. Now all the case of Non Co-operation Registration decisions is given by District Deputy Registrar [DDR] then society is registered
All flat owners should hold meeting and elect Promoter. All power for Registrations, documentation etc. should be given to promoter. The resolution should be passed and must be sign by all flat owners who wish to become member of the Co-operative Housing Society
Appoint Consultant / Legal Advocate for registration and ask him to comply all requirements. All members together also can do work for registration.

By |November 10th, 2018|SOCIETY FORMATION AND HANDOVER PROCESS BY BUILDER|Comments Off on SOCIETY FORMATION AND HANDOVER PROCESS BY BUILDER

Advocates for Society Formation in Pune

First general body meeting (before registration)
In this meeting under Society’s Model Bye-law 3(iii), the Chief Promoter (could be the builder) is primarily selected by the promoters, who are members co-signing the registration application before the Registering Authority, under Bye-law 3(xii).
Application for registration
Normally, the name reservation proposal should be accompanied with the society resolutions and signatures of at least 10 Promoters who have attended the meeting. On allotment of name and permission to open a bank account by the Registrar, the Chief Promoter has to collect Share Capital, Entrance Fees from promoters and deposit the same in the branch of the bank permitted by the Registrar. It should be noted that the amount cannot be withdrawn from the Bank till the society is registered or its registration is refused, except with prior written permission of the Registrar. The Chief Promoter should submit registration proposal to the registering authority within a period of 3 months from the date of issue of Letter of Reservation in the name of the proposed society.
Co-operative Societies Commissioner & Registrar’s GR No. SAGRUVO/1094/Pra.Kra 277/14C dated 10 March 1995 says “By exercising the powers in section 7 of the Co-operative Societies Act 1960 the government is pleased to exempt the provision of minimum 10 members for registering co-operative Housing society under sub-clause 1 in Section 6 of the said Act subject to the conditions that the plinth area of each flat in the proposed co-operative Housing Society should not be more than 700 sq. ft and FSI should not be balance for utilization in the proposed societies land/ building.
If builder/ promoter is not co-operating in registering the Co-operative Housing Society, then in that case, the application for registration of society be submitted in Form 6 (Rule 12) before the District Deputy Registrar, who has been given power under section 10(1) of the Maharashtra Ownership Flats Act 1963. While submitting the said proposal, a Notarized Indemnity Bond of the members who applied for the registration of society on the stamp paper of Rs. 200 is required.
Approval by Registrar
It is the duty of the concerned Registrar to register the Co-operative Housing Society, by scrutinizing the proposal submitted after fulfillment of above mentioned documents, and shall make an arrangement of issuing certificate of registration society under Section 9(1) of the Maharashtra Co-operative Society Act 1960, and copy of the registered bye-law, memorandum regarding registration of society to the chief promoter. The order regarding registration of society should have been sent for publishing in government gazette to the Government Printing Press for appropriate action. It is necessary to take decision on the registration of the society within a period of two months from the date of the proposal of the society submitted to the Registrar.
If proposal of society registration is denied or no decision is taken within two months then it is necessary to send that proposal to the Divisional Joint Registrar, Co-operative Societies under Section 152 of the Maharashtra Co. operative societies Act, can be approached.
First General Body Meeting obligatory Agenda (after registration):
• To elect a Chairman for the meeting
• To admit persons to membership who have applied for membership of the society.
• To elect a provisional Managing Committee
• To receive and approve the statement of account as prepared by the Chief Promoter of the society up to 14 days prior to the first general body meeting of the society.
• To authorize the committee to secure conveyance of right title and interest in the property in the name of the society from the promoter builder
• To impose restrictions on raising loan amount from outside
• To appoint internal auditor and to fix his remuneration
• To authorize one of the members of the provisional committee to call the first meeting of the provisional committee
• To take decision about taking membership of District Housing Federation and other institutions
• To give power to one member of provisional management committee to call meeting of the managing committee
• To consider the matters raised by the member except these matters which are necessary for giving advance notice with the permission of chairman and eleventh hour matter and to make resolution in that regard.

By |November 10th, 2018|Uncategorized|Comments Off on Advocates for Society Formation in Pune

Advocates for register a new housing Society

A co-operative society is the perfect fit for a residential building as flat-owners have common needs (water connection, watchmen, etc) and interests (maintenance of common areas, such as the terrace and compound). If you’ve purchased a flat in a new building, it would probably be best if you took interest in forming a society. The builder may also be statutorily obligated to form a society. For example, under Maharashtra Flat Ownership Act, 1963, a builder must form a society within four months of selling 60% of the flats.
But you needn’t wait for the builder to form the society. In many states, including Delhi and Maharashtra, ten flat-owners are enough to promote a co-operative housing society. A building without a housing society usually indicates that there is a dispute between members or a general lack of interest. If you’re considering buying a house in a building where the society has not been formed, find out what the problem is. If the builder does not form a society, rights to the terrace and the compound continue to rest with him.
We, the “VED LEGAL” provide registration and formation services which help you at every step of society formation, right from inception to final handover. We look after all the legal complications involved in society formation and carry out necessary negotiations with developers.
We have also completed the registration process for various projects. We specialize in society formation of housing societies, commercial societies, maintenance societies and large townships. We help developers and societies with complex registration process during society mergers, society split, and federation registrations.
Our specialized services include:
• Initial screening
• Gap identification and ratification
• Process documentation and finalization
• Dispute resolution
• Society name reservation at respective co-operative departments
• Account formation and legal documentation
FOR MORE DETAILS CALL:
VED LEGAL,
Adv. Gajanan Rahate
Mob: 9763040088
E_mail: [email protected]

By |November 10th, 2018|Advocates for register a new housing Society|Comments Off on Advocates for register a new housing Society

A COMPLETE GUIDE TO DEEMED CONVEYANCE

Most of the flat-owners of the newly constructed Societies/apartments do not have their sale deeds or conveyance deeds. Mostly in the newly constructed buildings, the builders provide for forming a housing co-operative society to which they shall transfer their interest in the property. Then the builders form the society but do not transfer the title of the property (read ownership) to the flat-owners or the society till he has transferred all the rights in the building/ Societies/apartments. Thus the builders/promoters are benefiting from the buyers lack of awareness and information.
To curb this practice, amendments were carried out in the Maharashtra Ownership Flats Act, 1963, in 2008 to appoint a Competent Authority (Registrar of Co-operative Housing Societies) to hear the grievances of such Societies/apartments owners and to safeguard their interest by executing deemed conveyance of such societies u/s 11(3) of Maharashtra Ownership Flats Act, 1963.
Ved Legal is having enough experience to deal with these kinds of Deemed Conveyance of Co-operative Housing Societies, in and around pune. Any aggrieved society or apartment holder can get resolution from us in regards of the same.

By |November 10th, 2018|A COMPLETE GUIDE TO DEEMED CONVEYANCE|Comments Off on A COMPLETE GUIDE TO DEEMED CONVEYANCE

Lawyers for Deemed Conveyance Process in Pune

Most of the flat-owners of the newly constructed Societies/apartments do not have their sale deeds or conveyance deeds. Mostly in the newly constructed buildings, the builders provide for forming a housing co-operative society to which they shall transfer their interest in the property. Then the builders form the society but do not transfer the title of the property (read ownership) to the flat-owners or the society till he has transferred all the rights in the building/ Societies/apartments. Thus the builders/promoters are benefiting from the buyers lack of awareness and information.
To curb this practice, amendments were carried out in the Maharashtra Ownership Flats Act, 1963, in 2008 to appoint a Competent Authority (Registrar of Co-operative Housing Societies) to hear the grievances of such Societies/apartments owners and to safeguard their interest by executing deemed conveyance of such societies u/s 11(3) of Maharashtra Ownership Flats Act, 1963.
Ved Legal is having enough experience to deal with these kinds of Deemed Conveyance of Co-operative Housing Societies, in and around pune. Any aggrieved society or apartment holder can get resolution from us in regards of the same.

By |November 10th, 2018|Lawyers for Deemed Conveyance Process in Pune|Comments Off on Lawyers for Deemed Conveyance Process in Pune

Advocates for Deemed Conveyance Process in Pune

Most of the flat-owners of the newly constructed Societies/apartments do not have their sale deeds or conveyance deeds. Mostly in the newly constructed buildings, the builders provide for forming a housing co-operative society to which they shall transfer their interest in the property. Then the builders form the society but do not transfer the title of the property (read ownership) to the flat-owners or the society till he has transferred all the rights in the building/ Societies/apartments. Thus the builders/promoters are benefiting from the buyers lack of awareness and information.
To curb this practice, amendments were carried out in the Maharashtra Ownership Flats Act, 1963, in 2008 to appoint a Competent Authority (Registrar of Co-operative Housing Societies) to hear the grievances of such Societies/apartments owners and to safeguard their interest by executing deemed conveyance of such societies u/s 11(3) of Maharashtra Ownership Flats Act, 1963.
Ved Legal is having enough experience to deal with these kinds of Deemed Conveyance of Co-operative Housing Societies, in and around pune. Any aggrieved society or apartment holder can get resolution from us in regards of the same.

By |November 10th, 2018|Advocates for Deemed Conveyance Process in Pune|Comments Off on Advocates for Deemed Conveyance Process in Pune